Multi-Job Purchase Requests: one PO across several jobs

One order to the supplier, with each line’s cost on the right job. Set the job on each Purchase Request line so Projected and Actual land where they belong.

Once Multi-Job Purchase Requests is enabled for your company, this is how Purchase Requests work.

You choose a Job on each line of the Purchase Request. You can use different jobs when the cost should split across jobs, or put the same job on every line when the whole order belongs to one job.

You still raise one Purchase Request, and the supplier still receives one Purchase Order.

Multi-Job Purchase Requests will be available from Tuesday 8 December. For early access, contact your Account Manager.

Watch the walkthrough:


What changes

Before Multi-Job is on for your company, you may still use the older method in How to Track a Single Purchase Order Across Multiple Jobs (leave the job blank on the Purchase Request, then add receipts on each job).

Once Multi-Job is on for your company, that workaround is no longer needed. Set the job on each line of the Purchase Request instead.

Examples of splitting across jobs:

  • Bulk materials shared across two project jobs

  • One supplier order that covers workshop and site work on different jobs


1. Create a Purchase Request

  • Go to Purchases and click Create Purchase Request, or create one from a Job

  • Fill in the usual details: Billable Company, Supplier, documents, delivery, and so on

  • Click Submit to continue to the line items


2. Add line items and set the job on each line

Add your items the way you usually do (manual entry, AI Quote Scan, or bulk upload).

On each line, set:

  • Job: the job that should carry that line’s cost

  • Invoiced back: tick if that line should be charged back to the client

Tip: Lines on the same Purchase Request can use different jobs, and can mix Invoiced back Yes and No.

If the whole order is for one job, put that same job on every line.


3. Save and send for approval

  • Check the totals

  • Click Save All

  • Click Send for Approval


4. After approval

When the Purchase Request is approved:

  • It converts to a Purchase Order as usual

  • Each Purchase Order line keeps the Job and Invoiced back from its Purchase Request line

  • The Purchase Order is not limited to a single job at the top of the page

  • The Invoiced back to client label on the Purchase Order shows if any active line is ticked

You can still edit line details where your process allows. A line’s subtotal can’t be saved below the amount already billed against it.


5. Match and approve supplier bills

Match supplier bills on Bills → Pending → Review & match. From the Purchase Order you may also see Match on Pending Bills. That opens the same screen.

Tick each Purchase Order line that appears on the invoice. The bar shows Matched so far and Left to match. When nothing is left to cover, approve the full bill.

When the bill doesn’t line up

Use the tools on that same screen to close the gap:

  • Split: only part of a Purchase Order line is on this bill. Split that line so the rest stays on the Purchase Order for a later bill.

  • Add adjustment: freight, rounding, or a small extra after every available Purchase Order line is already ticked. The amount goes onto the bill (and into Actual / net bill cost, shared across the jobs on that bill). It does not change Purchase Order line prices or Projected.

  • Raise variation: the bill is higher than what the Purchase Order has left to spend. The amount goes onto the bill against the job(s) you choose, and into Actual / net bill cost so you can approve. It does not change Purchase Order line prices or the Purchase Order subtotal, and it does not reduce what a bill line costs (use Apply credit for that).

  • Apply credit: the supplier has given you a credit. Allocate it to the bill lines it belongs to (a line can’t take more credit than was billed on that line). You can optionally attach the supplier credit note file. New credits can’t be created against the Purchase Order alone.

  • Approve as part-payment: some of the bill is matched, some is left, and the bill is not over the Purchase Order. Approve the matched amount now; the rest stays open for a later bill.

Once the bill is approved you can’t change Split, adjustments, or standard allocations. You can still Raise variation if the approved bill is still over the Purchase Order.

Important: A credit on a draft bill does not change Projected or Actual until the bill is Approved. A credit on a rejected bill never counts.


6. Money rules and reporting

Projected vs Actual

  • Projected Purchases = the Purchase Order subtotal for the job, before credits

  • Actual Purchases = what was really billed for that job after credits

Draft or rejected credits change neither figure.

Net bill cost

For each job, the net is: bill lines + adjustments − credits (excluding GST). That one figure is what Job Financials, WIP, P&L, and the Purchase Order screens use.

When credits count

Only on approved, active bills, applied to bill lines (capped at what that line billed). Credits lower Actual. Projected stays at the pre-credit Purchase Order amount.

Variations vs credits

  • A variation goes onto the bill for the job(s) you choose and into Actual. It does not rewrite Purchase Order lines or act as a credit.

  • A credit reduces what a bill line costs.

If billing goes past the Purchase Order

  • PO Balance shows the real shortfall (it can go negative)

  • Committed Costs on Project Plan stops at $0 so the forecast doesn’t hide the overspend

Same net everywhere

View Bill, Job Financials, WIP, P&L, and Purchase Order billed totals agree on the same net for each job. If one screen looks wrong, check the others against net bill cost first.

Simple example

Step

Projected

Actual

Purchase Order lines for the job total $1,000 excluding GST

$1,000

n/a

$1,000 bill approved

$1,000

$1,000

$100 credit applied and the bill is approved

$1,000 (unchanged)

$900


7. Closing a Purchase Order once there is an approved bill

Once a Purchase Order has an approved bill:

  • Cancel and Decline are refused

  • Use Close PO instead


FAQ

Is this optional?
No. Multi-Job Purchase Requests will replace the current way Purchase Requests work.

Can I still raise a Purchase Request for one job only?
Yes. Put the same job on every line (or raise it from that job as you do today).

Can lines mix Invoiced back Yes and No?
Yes. Tick Invoiced back per line. The Purchase Order label shows if any active line is ticked.

What’s the difference between a variation and a credit?
A variation goes onto the bill for the job(s) you choose and into Actual; it does not rewrite Purchase Order lines. A credit lowers what a bill line costs.

When do I Split vs Add adjustment?
Use Split when only part of a Purchase Order line is on this bill. Use Add adjustment for freight, rounding, or a small extra after every available line is already ticked. An adjustment goes onto the bill and into Actual; it does not change Purchase Order lines or Projected.

What happens on Tuesday 8 December?
Multi-Job Purchase Requests will be available from Tuesday 8 December. For early access, contact your Account Manager.

What about the old blank-job and receipts method?
Until Multi-Job is enabled for your company, that method remains valid. See How to Track a Single Purchase Order Across Multiple Jobs. Once Multi-Job is on for your company, use per-line jobs instead.

Where do supplier credits go?
Onto bill lines via Apply credit on the match screen, not as a new credit against the Purchase Order alone.


Summary

  • In Multi-Job purchase requests set Job and Invoiced back on each line (same job on every line if you don’t need to split)

  • One Purchase Request still becomes one Purchase Order for the supplier

  • Match bills on Pending Bills → Review & match. Use Split, Add adjustment, Raise variation, Apply credit, or part-payment when the bill doesn’t line up

  • Projected stays at the Purchase Order subtotal; Actual is net bill cost (lines + adjustments − credits)

  • Job Financials, WIP, P&L, and Purchase Order screens use that same net

  • Available from Tuesday 8 December (early access via your Account Manager)