Skip to main content

Record asset usage by quantity on timesheets

Enter Asset Qty and Asset Unit for asset entries so usage is costed and invoiced, and never counted as staff time.

Record how much of an asset was used as a quantity and unit, such as 1.5 Day or 3 Hours, so asset usage is costed and invoiced correctly and never counted as staff time.

If you don’t see Asset Qty and Asset Unit, contact support or your Account Manager to turn asset usage on.


1. Add asset usage in Staff Times

  • In Staff Times, add an asset entry

  • Choose the asset and job, then enter the Asset Qty (the quantity used, in the asset’s unit)

  • Save

Asset Qty is required. If it’s blank you’ll see "Enter a quantity".


2. Bulk Producing Times

  • Turn on the setting in Settings → Timesheet Settings to show Asset Qty and Asset Unit on Bulk Producing Times

  • Asset rows then save as usage entries with their quantity


3. Mobile app

When staff add an asset with a quantity in the mobile app, it’s saved as its own asset entry, separate from their own timesheet. That means it can be invoiced as its own line and shows in the Assets section of sign-off. An asset added without a quantity stays on the staff timesheet for information only.


4. Where asset usage shows

  • Staff Times: Asset Qty and Asset Unit columns

  • Client approval: asset rows show the quantity (for example "Excavator 1.5 Day") and stay out of the hours totals

  • Timesheet Report and Daily Claim Sheet PDFs: the Hours cell shows the quantity (for example "1.5 Day") and isn’t added to total shift hours

  • Job Timesheets totals: usage sits in an Asset Usage column and adds no hours

Asset usage is never counted as staff time, so it doesn’t flow into pay runs or payroll exports.


Summary

  • Enter Asset Qty for each asset entry; the unit comes from the asset

  • Turn on Asset Qty and Asset Unit for Bulk Producing Times in Timesheet Settings

  • Asset usage is costed and invoiced, but never paid as staff time

Did this answer your question?